Alemgena - Butajira
On Going / Road Projects
Accordingly the construction of Alemgena – Butajira Road design and Build project is one of the road way projects underway to improve the poor access throughout most parts of the country. For implementation of this project, the design is implemented by sub contract to STADIA CONSULTING ENGINEERS and the construction is under execution by YENCOMAD CONSTRUCTION PLC and the completed design was submitted to employer.
Project | Alemgena – Butajira Road Project |
Location | Amhara Regional state, North Shewa |
Employer | Ethiopian Roads Authority |
Consultant | Core Consulting Engineers PLC |
Contractor | YENCOMAD Construction Plc. |
Date of Commencement | March 1,2025 |
Original Contact Duration | 48 months (4 Years) Excluding 730 days of Defect liability & Including 120days of Mobilization |
Surface Type | Asphalt Concrete (AC) & Rigid Pavement |
Original Completion Date | February 28,2029 |
Rev. Completion Date | |
Initial Contract amount including VAT | ETB 14,067,998,448.59ETB |
Original Contract Length | 120Km |
The Federal Democratic Republic of Ethiopia as part of its Road Sector Development Program has allocated sufficient budget for the construction of 60 km (Original contract length) from Alemgena – Butajira (120Km) Road . Accordingly the Ethiopian Roads Authority (ERA), acting as duly authorized representative of the government, has signed a contract agreement with our company, Yencomad Construction Pvt. Ltd. Co., on March 1,2025 (Letter to be delivered).