Endeto Gasera Gravel
Completed / Road Projects
Project Name: | Endeto Gasera Gravel |
Road Type: | Gravel Wearing |
Project Length (km): | 60.3 |
Name of Employer: | Ethiopian Roads Authority |
Award Date: | Dec. 11,2007 |
Completion Date: | 11/20/2012 |
Brief description of the works performed: Gravel surface finished 60 km road works (Earth works mainly rock excavation 6,513,290; rock excavation (m3) 3,603,592 surface course 105,000.0 m3).
Huge volume of earthwork encountered in quantity and price escalations.
Original contract duration was 1096 calendar days , which was extended to 1806 calendar days.