Corridor and Road Expansion
On Going / Road Projects
This construction activity is being undertaken by Yencomad Construction PLC under the supervision of G & Y Engineering Consult P.L.C. The Addis Ababa City Roads Authority, acting on behalf of the Government of Ethiopia, allocated a sufficient budget for the development of this vital infrastructure project.
The contract was officially signed between the Addis Ababa City Roads Authority and Yencomad Construction PLC, with the works commencing on 15 November 2024. The total initial contract value, including VAT, is 1,939,594,873.19 ETB. As of the latest update in July 2023, approximately 86% of the project has been successfully completed, with significant progress on the asphalt surface roads, bicycle lanes, walkways, utility lines, and other associated infrastructure.
Project : | Addis International Convention & Exhibition ,CMC-Summit-Goro-VIP-Bole Terminal Corridor Development Project Section Two: – CMC-SUMMIT and Section Three: Summit-Goro |
PROJECT SCOPE: | Asphalt Surface Roads,Bicycle Lanes,Walkways,Utility Lines,Box Culvert and Associated River Training Structures ,Four Parking Lots,One Terminal |
Location: | Addis ababa |
Employer: | Addis Ababa City Roads Authority |
Consultant: | G & Y ENGINEERING CONSULT P.L.C |
Contractor: | Yencomad Construction PLC |
Date of Commencement : | 15 November, 2024 |
Original Contact Duration | Less than 181 Calendar Days |
Rev. Contract Duration | 181 Calendar Days |
Completion Date | 14 May, 2025 (there is EoT) |
INNITIAL CONTRACT AMOUNT: | 1,939,594,873.19 ETB Including VAT |
Original Contract Length | 5 km |
PROJECT: Addis International Convention & Exhibition ,CMC-Summit-Goro-VIP-Bole Terminal Corridor Development Project Section Two: – CMC-SUMMIT and Section Three: Summit-Goro / and EMPLOYER: Addis Ababa City Roads Authority and CONSULTANT: G & Y ENGINEERING CONSULT P.L.C and CONTRACTOR: YECNOMAD CONSTRUCTION P.L.C. and LENGTH: and 5km length and PROJECT SCOPE: Asphalt Surface Roads,Bicycle Lanes,Walkways,Utility Lines,Box Culvert and Associated River Training Structures ,Four Parking Lots,One Terminal and
INNITIAL CONTRACT AMOUNT:1,939,594,873.19 ETB Including VAT and COMMENCEMENT DATE:15 November, 2024 and COMPLETION DATE:14 May, 2025 (there is EoT) and ACCOMPLISHMENT: 86%