Efeson - Mehal Meda
On Going / Road Projects
Accordingly the construction of Efeson/Ataye-Mehalmeda Road design and Build project is one of the road way projects underway to improve the poor access throughout most parts of the country. For implementation of this project, the design is implemented by sub contract to STADIA CONSULTING ENGINEERS and the construction is under execution by YENCOMAD CONSTRUCTION PLC and the completed design was submitted to employer.
Project | Efeson(Ataye)-Mehal Meda Road Project |
Location | Amhara Regional state, North Shewa |
Employer | Ethiopian Roads Authority |
Consultant | Core Consulting Engineers PLC |
Contractor | Yencomad Construction PLC |
Date of Commencement | April 24, 2015 |
Original Contact Duration | 1096 Calendar Days |
Rev. Contract Duration | 1512 Calendar Days |
Original Completion Date | April 24, 2018 |
Rev. Completion Date | June 13, 2019 [There is request of EOT] |
Initial Contract amount including VAT | 1,352,642,535.82 ETB |
Original Contract Length | 60 Km |
Current Progress | 96% completed until the project was stopped due to security problem. |
The Federal Democratic Republic of Ethiopia as part of its Road Sector Development Program has allocated sufficient budget for the construction of 60 km (Original contract length) from Efeson(Ataye)-Mehal meda Road to DS5 standard. Accordingly the Ethiopian Roads Authority (ERA), acting as duly authorized representative of the government, has signed a contract agreement with our company, Yencomad Construction Pvt. Ltd. Co., on April 24, 2015 for works construction of this road project. Currently, the project is almost substantially completed.